Construction Update: May 30, 2013 to June 12, 2013


Posted by J. Eagan

During this period, Milestone Construction Company:

  • Continued installation of exterior sheathing and air and vapor barrier work
  • Began installation of exterior roof blocking, roof insulation and ice & water shield at the low roof areas
  • Continued installation of exterior brick masonry
  • Continued installation of the clerestory storefront frames and glazing, which is 66% complete
  • Continued mechanical, plumbing and electrical rough-ins
  • Installed ship's ladder
  • Started installation of the bridge abutments
  • Dug trench for waterproofing