Construction Update: May 16, 2013 to May 29, 2013


Posted by J. Eagan

During this period, Milestone Construction Company:
  • Continued installation of exterior sheathing, blocking and air and vapor barrier work
  • Continued mechanical, plumbing and electrical rough-ins
  • Continued installation of exterior brick masonry and metal roofing
  • Commenced framing at high bulkheads
  • Continued installation of the main sprinkler runs
  • Began waterline relocation