Posted by J. Eagan
During this period, Milestone Construction Company:
- Re-worked piping to water meter vault
- Continued installation of the interior and exterior cold frame metal
- Continued installation of exterior sheathing and air and vapor barrier work
- Continued mechanical, plumbing and electrical rough-ins
- Continued installation of exterior brick masonry, which is approx. 35% complete