Construction Update: April 4, 2013 to April 17, 2013

Posted by J. Eagan

During this period, Milestone Construction Company:

  • Passed TPF inspection
  • Installed the USG-2, PT-2, SW-2 and MH-15
  • Started installation of the metal roofing from 2-3 and 4-5 gridways
  • Commenced installation of the rigid insulation
  • Started installation of the air and vapor barrier
  • Installed and tested the underground sprinkler pipe; passed inspection
  • Continued to install LGSSF
  • Continued plumbing and electrical rough-in
  • Completed installation of the brick column enclosures in the adult reading area
  • Commenced installation of the steel plates to box existing WF beams