Construction Update: April 18, 2013 to May 1, 2013

Posted by J. Eagan
During this period, Milestone Construction Company:

  • Continued SWM work
  • Reset water meter vault
  • Continued concrete work at the stairs, water service room and at the column "diamonds"
  • Continued installation of interior and exterior cold frame metal
  • Continued installation of exterior sheathing and air and vapor barrier work
  • Commenced below grade brick masonry installation
  • Continued mechanical, plumbing and electrical rough-ins
 