Posted by J. Eagan
During this period, Milestone Construction Company:
- Continued installation of the roof insulation, sheathing, and ice and water shield at the high sloped roof areas
- Continued to install the CMU
- Commenced installation of the electrical room switchgear
- Continued installation of the electrical rough-in
- Started installation of the plumbing and gas pipe work
- Continued installation of framing at clerestory