Construction Update: December 13, 2012 to January 9, 2013

During this period, Milestone Construction Company:

  • Continued duct bank work;
  • Worked on under slab electrical installation in Area 1;
  • Continued masonry wall work;
  • Poured the mezzanine slab; and
  • Did miscellaneous steel and mechanical piping work for the radiant heaters.