Construction Update: January 10, 2013 to January 23, 2013

During this period, Milestone Construction Company:
  • Continued under-slab electrical work and slab prep at Area 2 slab-on-grade;
  • Continued installation of wood roof blocking;
  • Continued installation of masonry at mezzanine level;
  • Started new masonry openings at wall along 1-gridline; and
  • Continued installation of roof curbs for mechanical equipment.
Posted by J. Eagan
 