During this period, Milestone Construction Company:
- Continued under-slab electrical work and slab prep at Area 2 slab-on-grade;
- Continued installation of wood roof blocking;
- Continued installation of masonry at mezzanine level;
- Started new masonry openings at wall along 1-gridline; and
- Continued installation of roof curbs for mechanical equipment.