During this period, Milestone Construction Company:
- Completed Installation of footings and most foundation walls;
- Began grouting and backfilling of foundation walls;
- Began digging the trench and other work associated with duct bank installation;
- Finshed erecting steel framing, required to support the glu-lam beams;
- Began erection of other steel framing;
- Began Installation of glu-lam beams;
- Began installation of wood decking; and
- Continued with Inspections and testing.
Posted by R. GaleLabels: Construction, Olney, Olney Library