Construction Update: November 29-December 12, 2012

During this period, Milestone Construction Company:
  • Continued wood decking installation;
  • Started masonry wall repair near meeting room;
  • Started preparing the slab on grade in the Children's area;
  • Completed electrical conduit work;
  • Dug the trench for the ductbank;
  • Completed removal of existing roofing from gridlines 1 to 2;
  • Started rebar installation and prep work for the mezzanine slab; and
  • Completed excavation for metal vault installation. 

Posted by R. Gale