Construction Update: November 2-November 14, 2012

During this period, Milestone Construction Company:
  • Continued erecting interior columns, miscellaneous columns and beams;
  • Began installation of sleeves through deck of mezzanine;
  • Continued installation of glu-lam beams;
  • Installed the high roof wood decking from 2.1 to 2.9; and
  • Continued backfilling, grading, and removal of mud and debris from the Children's, Young Adult, and public toilet room areas. 

Posted by R. Gal