During this period, Milestone Construction Company:
- continued cleaning salvaged bricks (removal of loose mortar particles);
- continued concrete slab removal;
- continued miscellaneous selective demolition;
- continued debris removal
- started layout of footings at the addition area; and
- began tying rebar mats.
The construction project has been underway 100 days.