Construction Update: July 26 to August 8, 2012

During this period, Milestone Construction Company:
  • completed concrete slab removal;
  • continued layout of peers and footings at the addition area;
  • completed approximately 60% of water line installation;
  • completed selective masonry demolition; and
  • held an electrical pre-con meeting.

The construction project has been underway 128 days.  98% of demolition work is complete and Milestone expects to begin erecting steel in the next two weeks.