Construction Update: July 12 to July 25, 2012

During this period, Milestone Construction Company:
  • continued saw cutting and removing existing slab on grade;
  • continued selective roof demolition;
  • installed MH-15, MH-16, and MH-17 and connecting pipes;
  • began grading of building pad;
  • installed footings along x-gridlines;
  • began installation of piers; and
  • installed water line stub inside building.

The construction project has been underway 114 days.