Construction Update: August 9 to August 22, 2012

During this period, Milestone Construction Company:
  • continued layout of columns, piers, anchor bolts and footings in all areas;
  • removed beam from shoring under one of the roof sections;
  • held a steel pre-con meeting;
  • began erecting steel; and
  • completed approximately 50% of the beams in the center high roof area.
The construction project has been underway 142 days.  A construction crane is now on site for erecting the steel.