Construction Update: June 13 to June 27, 2012

During this period, Milestone Construction Company:
  • continued selective demolition of exterior masonry walls, foundation walls and penthouse slab;
  • began saw-cutting slab on grade;
  • began rough grading of building pad;
  • continued removing excess fill and hauling debris from the site;
  • met with WSSC representatives;
  • set sanitary at end of existing line, and
  • began cleaning salvaged bricks (removal of loose mortar particles). 
The construction project has been underway eighty six days.
Posted by R. Gale
 