Construction Update: May 2 to 16, 2012

Olney Library entrance
During this period, Milestone Construction Company:
  • completed salvage of the "Delights of Reading" mosaic mural and arranged for offsite storage;
  • completed salvage of three of the four glu-lam beams that will be reused during the renovation and wrapped them for storage on the library site;
  • began selective pavement, interior, roof, and floor slab demo;
  • shored up existing walls and roof;
  • participated in a masonry recovery meeting;
  • began underpinning of the existing foundation;
  • staked out the stormwater management area; and
  • arranged for delivery of storm/sanitary structures to the site.
The construction project has been underway forty four days.