Pages

Monday, May 14, 2012

Construction Update: April 2 to April 18, 2012

Olney Library entrance
During this period, Milestone Construction Company: 
  • installed the project sign on the site;
  • installed and inspected the trailer and temporary power to the trailer;
  • completed refrigerant recovery;
  • completed a fixture count (done by WSSC)
  • participated in a preconstruction meeting for demolition;
  • began grubbing and tree clearance; and
  • began interior scrap out and selective interior demolition.
  • The construction contract has been underway for sixteen days.

Posted by R. Gale.

No comments: